Overview
Name The implementation of integrated land development programmes for Establishment of a Basin Management Framework for the Integrated Management of the Tisza Transboundary River (Tisza MSP)
Practice
The implementation of integrated land development programmes
Project
Integrating multiple benefits of wetlands and floodplains into improved transbou ...
Beneficiary country: Tisza Countries
Region:
Beneficiary country
Central and Eastern Europe
Danube-Black Sea
Details
Analysis – Why the BMP worked or did not work?: In Progress
Lessons learned: Land ownership issues more complex and time consuming that originally thought
Comments: UA, SK, HU, RO, and RS
Implementation start date:
2008-01-01
Implementation end date:
2011-12-31
Link to project documents: Project documents www.icpdr.org/undp-gef-tisza
Link to project reports: Project reports www.icpdr.org/undp-gef-tisza
Results
Annual tons of nitrogen reduced: N/A
Annual tons of phosphorous reduced: N/A
Other outcomes: Development of an Integrated River Basin Management Plan linking the requirements and objectives of the EU Water Framework Directive, Flood Directive with improved land and water management
Finance
Total co-finance (USD): 1 M
Total GEF/WB investment: USD 1.0 million
Contacts
Co-finance partners: ICPDR, EC, UNEP, Coutries of the Tisza Basin www.icpdr.org
Project Manager:
Peter Whalley