Project Name Country Province Location1


North     East
Installed Capacity1
(MW)
Status Developer/*
Promotor
(Country)
Dam Height1
(m)
Rated Head1
(m)
Inundated
Area1 (km2)
Pak Beng
Lao PDR
Oudomxay
19'52.7" 101'08.7" 1,230
MOU signed 29/08/2007
Datang International Power
Generation Co. Ltd.
(China-Hong Kong)
62.1 20 110
Luang Prabang
Lao PDR
Luang Prabang
20'05.0" 102'10.4" 1,410
MOU signed 14/10/2007
PetroVietnam Power Corporation
(Viet Nam)
68 20 110
Xayaboury
Lao PDR
Xayaboury
19'15.1" 101'48.8" 1,260
MOU signed 04/05/2007
Ch.Kanchang & PT
(Thailand)
53 16.26 30
Pak Lay
Lao PDR
Xayaboury
18'19.5" 101'31.6" 1,320
MOU signed 11/06/2007
CIEC & Sinohydro
(China)
54.5/45.5 18 110
Pak Lay
Lao PDR
Xayaboury
18'19.5" 101'31.6" 1,320
MOU signed 11/12/2007
Datang International Power
Generation Co. Ltd.
(China-Hong Kong)
38 18  
Sanakham
Lao PDR
Vientiane
17'57.3" 101'25.0" 570
*Department of Alternative Energy
Development and Efficiency, MoE,
Thailand
(Thailand)
55 25.5 80
Ban Khoum
Lao PDR/ Thailand
Champassak/
Ubon Ratchathani
15'25.1" 105'35.2" 2,000 MOU signed 25/03/2008
Italian-Thai Development PLC &
Asia Corp, Holdings Limited.
(Italy-Thailand)
53 25.5 158
Lat Sua
Lao PDR
Champassak
15'19.2"
105'37.0"
800
MOU signed 02/04/2008
Charoen Energy and Water Asia Co. Ltd.
(Thailand)
     
Don Sahong
Lao PDR
Champassak
13'57.4" 105'57.8" 360
MOU signed 23/3/2006
PDA signed 13/02/2008

Mega First Corporation Berhad
(Malaysia)
10.6/8.2 /8.3   1.6
Stung Treng
Cambodia
Stung Treng
13'33.0" 105'57.0" 980       22 640
Sambor (0ption 1)
Cambodia
Kratie (Sambor)
12'35.0" 106'01.0" 2,600       54 880

Sources: Lao National Mekong Committee and MRC databases